Capital Works in Progress

Our 2024/25 Capital Works

In its capital works program, Council has planned expenditure of $26.9 million for 2024/25 including a total budget of about $7.988 million for major projects.

Importantly, Council is fully funding its renewal demand in transport, stormwater and property assets – to ensure that the level of service provided to the community by our roads, footpaths, drainage, community buildings and recreation facilities is maintained.

Capital projects for 2024/25 include:

  • Commence the project to repair and reopen the Glenorchy War Memorial Pool
  • Construct the Berriedale-Windermere Foreshore trail
  • Complete Soccer projects at KGV and North Chigwell
  • Construct the Claremont Pump Track and Skate Ramp
  • Extend the life of the Jackson Street landfill
  • Resurfacing up to 7.3km of roads (2% of network)
  • Replacing up to 4.1km footpaths  (1% of network)
  • Stage 2 Road Reconstructions in Ashbourne Grove and Renfrew Circle
  • Cycling Grant – Stage 1B – Main Road Granton Shared Path
  • Black Spot Projects in Grove Road, Main Road Austins Ferry and Kensington Street
  • Vulnerable Road User Projects in Gavitt Street, Wrights Avenue, Bayswater Road and Bowden Street
  • Replacement of various picnic shelters, seating, tables and BBQs
  • Public toilet replacement at Berriedale Bay
  • Redlands Drive flood mitigation (sedimentation basin)
  • Chandos Drive stormwater upgrade (190 Marys Hope Road)
  • Chapel Street Reserve DN300 replacement
  • New Town Rivulet Outlet Redevelopment – (CoH project)

Where are the Planned Works Happening?

We perform ongoing works all year round as part of scheduled maintenance, capital works and operational management of Council’s assets.

To view a map of Council’s assets and planned Capital works, click the link below and select the layer ‘Capital Works’

Scheduled works are subject to change due to weather and other circumstances. If you have any enquiries please contact Council.

Stormwater Works

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Cordelia Court Overland Flow PathWed 19/03/25Mon 5/05/2515%
Chandos Drive Stormwater DiversionTue 3/12/24Fri 14/02/25100%
150 Fairy Glen Road – formalise overland flow access roadMon 5/05/25Tue 27/05/250%
Hilton Road – Chippendale Street storm water mitigationTue 11/03/25Tue 18/03/25100%
Abbotsfield Park DN600 Replacement – Stage 1Tue 25/06/24Mon 2/12/24100%
Glenmore Street – pit replacementMon 15/07/24Tue 30/07/24100%
Bowden Street – pit replacementMon 2/09/24Mon 16/09/25100%
Black Snake Road – roadside drainage extensionMon 21/10/24Fri 24/01/25100%
Fenwick Crescent – outlet upgradeMon 17/02/25Mon 24/02/25100%
Chapel Street Reserve Southern DN300 Replacement – Stage 1Tue 6/05/25Mon 26/05/250%
Driscoll Street – relining and connectionsMon 1/07/24Mon 1/07/240%
Coleman Street – relining and connectionsMon 1/07/24Mon 1/07/240%
Hamel Street – pipe repair and bank rehabilitationMon 5/05/25Tue 13/05/250%
Ecosol GPT upgrade – stage 2Mon 1/07/24Mon 1/07/240%
Jacques Creek – erosion protection / reinstatement worksMon 24/03/25Tue 29/04/250%

Road Resurfacing

Reseal ProgramEstimated Start DateEstimated Finish DatePercentage Complete
Albert Road – from Station Street to Gatehouse StreetSun 16/03/25Sun 16/03/250%
Albert Road – from Gatehouse Street to Central AvenueMon 17/03/25Mon 17/03/250%
Albert Road – from Central Avenue to Fletcher AvenueTue 18/03/25Tue 18/03/250%
Albert Road – from Fletcher Avenue to Bowen RoadWed 19/03/25Thu 20/03/250%
Albert Road – from Bowen Road to Cotswold PlaceMon 24/03/25Tue 25/03/250%
Albert Road – from Cotswold Place to Risdon RoadWed 26/03/25Thu 27/03/250%
Barossa Road – from Tolosa Street to Oxford CrescentThu 10/10/24Fri 11/10/24100%
Barossa Road – from Burton Street to Dickson StreetMon 14/10/24Tue 15/10/24100%
Berriedale Road – from Croome Court to Chandos DriveMon 17/02/25Tue 18/02/250%
Berriedale Road – from Chandos Drive to Marys Hope RoadMon 24/02/25Tue 25/02/250%
Chapel Street – from Main Road to Kensington StreetSun 10/11/24Sun 10/11/24100%
Chapel Street – from Kensington Street to Hull StreetMon 11/11/24Tue 12/11/24100%
Chapel Street – from Hull Street to Massey StreetWed 13/11/24Thu 14/11/24100%
Chesterman Street – from Derwent Park Road to the end of the roadThu 28/11/24Thu 28/11/24100%
Sunderland Street – from Sunderland Street to Chesterman StreetFri 29/11/24Fri 29/11/24100%
Main Road – from Chapel Street to Grove RoadSun 24/11/24Tue 26/03/25100%
Springdale Road – from Collinsvale Road to Aurora Pole 47Wed 12/03/25Wed 12/03/250%
Springdale Road – from Aurora Pole 47 to Aurora Pole 38Thu 13/03/25Thu 13/03/250%
Collins Cap Road – from Springdale Road to Aurora Pole 161Fri 24/01/25Fri 24/01/250%
Junee Street – from Danina Street to Kilpa StreetWed 25/06/25Thu 26/06/250%
Christie Avenue – from Lawson Street to Milton CrescentMon 16/06/25Mon 16/06/250%
Milton Crescent – from Lawson Street to end of the roadWed 23/03/25Tue 24/03/250%
Montrose Road – from House Number 124 to Nielson DriveMon 30/06/25Mon 30/06/250%
Kalang Avenue – from Bimburra Road to Aurora Pole 30Wed 18/12/24Wed 18/12/24100%
Kalang Avenue – from Aurora Pole 30 to Aurora Pole 23Thu 19/12/24Thu 19/12/24100%
Kalang Avenue – from Aurora Pole 23 to the council boundaryFri 20/12/24Fri 20/12/24100%
**Click the button above to see map locations of these works**

Bridge Renewal

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
New Town Rivulet – walkway undermining repairMon 5/05/25Tue 3/06/250%
Islet Rivulet – abutment repointingThu 8/05/25Mon 22/05/250%
Tolosa Park Bridge – frame repairTue 22/4/25Fri 9/05/250%
Walkway Bridge – corrosion protection worksMon 26/05/25Wed 18/06/250%
**Click the button above to see map locations of these works**

Footpath Renewal

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Main Road CBD Footpath (from Gavitt Street to Elwick Road) footpath replacementTue 2/07/24Mon 9/09/24100%
Karambi StreetMon 1/07/24Wed 23/10/24100%
Left footpath on Kilpa Street – Allunga Road to Junee StreetWed 26/05/25Mon 28/07/250%
Right footpath on Kilpa Street – Allunga Road to Junee StreetMon 29/07/25Fri 26/09/250%
Left footpath on Howard Road – Dodds Avenue to Gepp ParadeMon 2/06/25Thu 5/06/250%
Right footpath on Howard Road – Dodds Avenue to Gepp ParadeFri 6/06/25Tue 1/07/250%
Left footpath on Howard Road – Gepp Parade to House no. 96Tue 2/07/25Wed 23/07/250%
Left footpath on Howard Road – House no. 96 to Havelock AvenueWed 2/07/25Wed 23/07/250%
Right Footpath on Junee Street – Danina Street to Kalipa StreetMon 28/10/24Fri 14/03/2595%
Left Footpath on Junee Street – Danina Street to Kalipa StreetMon 17/03/25Wed 25/06/250%
Right footpath on Bayswater Road – Gormanston Road to Orchard RoadThu 10/04/25Fri 9/05/250%
Left footpath on Bayswater Road – Gormanston Road to Orchard RoadMon 12/05/25Tue 3/06/250%
Left footpath on Milton Crescent – Lawson Street to the end of the roadMon 4/11/25Mon 31/03/2580%
Right footpath on Milton Crescent – Lawson Street to the end of the roadTue 1/04/25Thu 10/07/2580%
Right footpath on Barossa Road – Oxford Crescent to Burton StreetMon 16/12/24Mon 23/12/24100%
Left footpath on Barossa Road – Tolosa Street to Oxford CrescentMon 24/02/25Tue 11/03/25100%
Right footpath on Chesterman Street – Derwent Park Road to the end of the roadMon 14/10/24Wed 30/10/24100%
Left footpath on Chesterman Street – Derwent Park Road to the end of the roadThu 31/10/24Thu 14/11/24100%
Left footpath on Sunderland Street -Sunderland Street to Chesterman StreetTue 3/09/24Tue 17/09/24100%
Left footpath on Aldridge Court – Chatterton Court to House no. 16Mon 2/06/25Tue 17/06/250%
Footpath – 4861 Purdie StreetMon 4/11/24Mon 11/11/24100%
Right footpath on Tamara Court – Casuarina Crescent to the end of the roadTue 30/07/24Thu 31/10/24100%
MONA footpath upgrade – part 2Mon 15/07/24Mon 29/07/24100%
ROW Canberra Road – laneway and stair repairsMon 28/01/25Wed 12/02/25100%
**Click the button above to see map locations of these works**

New Footpath and Cycleway Construction

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
KGV Pedestrian Crossing – near Wrights AvenueMon 3/03/25Tue 14/03/25100%
Main Road Granton – shared path – Stage 1Mon 22/07/24Thu 17/10/24100%
Berriedale Foreshore Reservation connectionMon 3/06/24Thu 11/07/24100%
Bowen / Bayswater Road Footpath and Kerb RampsWed 2/04/25Wed 9/4/250%
Bowden Street to Terry Street – footpath realignmentMon 20/01/25Fri 7/02/25100%
Kensington Street – school crossingTue 15/04/25Thu 22/05/250%
**Click the button above to see map locations of these works**

Pavement Rehabilitation

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Fenwick Crescent – from Lampton Avenue to Gepp ParadeMon 24/03/25Wed 26/03/250%
Cammeray Road – from Bradfield Street to Spring Street – (Stage 1)Tue 27/05/25Th 28/08/250%
Renfrew Circle Road – reconstruction and traffic improvementMon 8/04/24Fri 1/11/24100%
Ashbourne Grove Stage 2 – Garden Grove resealWed 30/10/24Tue 27/05/2560%
**Click the button above to see map locations of these works**

Road User Safety Improvement

Program NameEstimated Start DateEstimated Finish DatePercentage Complete
Anfield Street – intersection worksMon 13/01/25Thu 17/04/2595%
Main Road – safety barrier and footpathMon 26/05/25Wed 25/06/250%
Main Road to Cadbury Road – proposed kerb realignmentMon 31/03/25Wed 7/05/250%
Mentmore Street – kerb rampsMon 28/04/25Tue 27/05/250%
Inner-city Cycleway – Sunderland Street crossingMon 26/05/25Mon 10/06/250%
Collins Cap Road – guardrail extensionMon 21/10/24Wed 23/10/24100%
Main Road to Claremont Link Road – guardrail worksMon 28/10/24Mon 11/11/2490%
**Click the button above to see map locations of these works**